The guys got back today from the village. They hauled over 30 pick-up loads of dirt to fill in our foundation! The building team took a break so that they could just shovel the dirt from the pickup right into the house. The team got started again when they’d finished the fill. We have 6 rows of bricks up as of Monday. Every day, they do 2 more rows of bricks. And, there are about 20 rows all together. It’s going fast now!
There is a work team coming this weekend, so on Monday, the guys will head back to the village with them. They’re hoping to be able to pour our cement floor and our bond-beam on top of the adobe walls! It’s moving along!